ERRCS Requirements in Texas: Houston, Dallas, Austin & San Antonio

If you are building, renovating, or leasing commercial space in Texas, the fire marshal will likely ask whether police and fire radios work inside your building. If they don’t, you may need an Emergency Responder Radio Coverage System (ERRCS) before you get a Certificate of Occupancy. However, Texas has no single statewide ERRCS rule. Houston, Dallas, Fort Worth, Austin and San Antonio each enforce their own version, and the details can change your design, your schedule and your budget.

This guide explains how ERRCS requirements work in Texas, what each major city requires, and how to keep your project on schedule.

What Is an ERRCS?

An ERRCS is an in-building system that carries first responder radio signals into areas where they would otherwise drop out, such as stairwells, basements, parking garages and the core of large buildings. It typically includes a rooftop donor antenna, a bi-directional amplifier (BDA), and indoor antennas and cabling on every floor. Texas cities use different names for the same system: Houston calls it Emergency Responder Communication Coverage (ERCC), San Antonio uses ERRC and two-way radio enhancement system, and many plans say ERCES or public safety DAS. Learn more about ERRCS installation.

Does Texas Have a Statewide ERRCS Requirement?

No. In Texas, cities adopt their own edition of the International Fire Code (IFC), add local amendments, and enforce them through their own fire marshal and building departments. Section 510 of the IFC is where the radio coverage rules live. Outside city limits, state law allows larger counties, and counties next to them, to adopt a fire code of their own (Texas Local Government Code § 233.061). As a result, two buildings an hour apart can face very different requirements. Your first step is always to confirm which Authority Having Jurisdiction (AHJ) covers your address.

ERRCS Requirements by Texas City

Houston

Downtown Houston high-rise buildings that may require ERRCS under Houston Fire Code Section 510

Houston’s rules are spelled out in its Emergency Responder Communication Coverage guideline, Form CE-1350, are based on Houston Building Code Section 918, and Houston Fire Code Section 510. Key points include:

  • Who it applies to. New buildings, remodels of existing buildings, and lease buildouts. Buildings with no basement, three stories or less, and no more than 50,000 sq ft in total are exempt.
  • Pre-installation test. A coverage test is required before any BDA is installed, to show whether a system is needed.
  • Engineer-sealed plans. ERRCS plans must be designed, sealed, signed and dated by a Texas Professional Engineer.
  • Post-installation test. Before the Certificate of Occupancy, a City of Houston registered ERRCS special inspector must test the system.
  • Frequencies. Project frequencies come from City of Houston HITS or the Harris County Radio Network Operation Center.

Since May 1, 2026, the Houston Fire Marshal’s Office has been the main point of contact for ERRCS compliance documents, while Building Code Enforcement still registers designers, installers and special inspectors (Houston Permitting Center notice). See our Houston ERRCS testing services.

Dallas

Dallas, Texas skyline at night, where buildings follow ERRCS requirements in the Dallas Fire Code

Dallas enforces the Dallas Fire Code, which is the 2021 IFC with Dallas amendments. Section 510, titled Emergency Responder Communication Coverage, requires buildings to provide the radio signal strength first responders need (City of Dallas memo). Dallas Fire-Rescue reviews ERRCS plans and witnesses testing, so confirm current submittal requirements before design. Learn more about ERRCS installation in Dallas.

Fort Worth

The Fort Worth Fire Department applies 2021 IFC Section 510 along with NFPA 1221 and 1225 (Fort Worth Bureau of Fire Prevention Q&A). Highlights include:

  • When a test may be required. Buildings over 3 stories, over 100,000 sq ft, of Type IA or IB construction, or with RF-blocking construction or windows.
  • High-rises. Any high-rise requires an ERRCS with a distributed antenna system and BDA.
  • Test timing. The signal strength test happens at substantial completion, after walls, windows and insulation are installed, and must be done by a licensed or certified radio contractor.
  • Permits. Submitted through the FWFD online portal, with floor plans, UL 2524 product data and FCC signal booster registration.

Austin

Austin, Texas skyline at sunset, where new buildings need ERCES approval from the Austin Fire Department

Austin reviews ERCES plans against the 2021 IFC with local amendments and the 2019 edition of NFPA 1221. Submittals must include:

  • Qualifications. A copy of the designer’s FCC General Radio Operator License (GROL) and proof of in-building system training.
  • Listed equipment. FCC-certified amplifiers and UL 2524-listed headend equipment.
  • Backup power. Documentation showing the 12-hour standby battery requirement is met.
  • Design documents. Floor plans, a riser diagram and a color signal strength (propagation) map.
  • Monitoring and records. A monitoring panel in the fire command center for high-rises, and a record cabinet for the owner’s annual test results.

Austin’s Wireless Communication Services Division provides radio frequency and donor site information. See our Austin ERRCS testing services.

San Antonio

San Antonio adopted the 2024 IFC with local amendments, effective May 1, 2025 (San Antonio fire code amendments). Its ERRC design bulletin (IB 601, revised October 1, 2026) requires:

  • Qualified designers and installers. At least one of an FCC GROL, NICET certification in emergency responder radio systems, ETA certification in distributed antenna systems, or a Professional Engineer approved by the AHJ, plus in-building system training.
  • City registration. The installing contractor must be registered with the City.
  • Written consent before activation. The City must give written approval before any system is turned on, and installation cannot start until plans are approved.

San Antonio also has specific rules for existing buildings (IB 603). Owners may be required to survey their building’s radio coverage using 20 test grids per floor, with a passing level of -95 dBm and a delivered audio quality (DAQ) of 3.0. If a system is required, the owner has three years to comply, with deadlines for hiring a contractor, permitting and installation. Learn more about ERRCS installation in San Antonio.

Other Texas Cities

Cities like Plano, Frisco, Irving, Arlington, Katy and Georgetown adopt their own fire code editions and amendments, and some publish their own ERRCS specifications. Always request the local requirements from the fire marshal before design begins.

CityFire code basisWhat stands out
HoustonHouston Fire Code §510, Building Code §918Texas PE-sealed plans, registered special inspector, exemption for small buildings
Dallas2021 IFC with Dallas amendmentsSection 510, Emergency Responder Communication Coverage
Fort Worth2021 IFC §510, NFPA 1221 and 1225Test triggers: 3+ stories, 100,000+ sq ft; high-rises always require a system
Austin2021 IFC with local amendments, NFPA 1221 (2019)GROL required in submittal, 12-hour battery, UL 2524 headend
San Antonio2024 IFC with local amendmentsCity-registered installer, written consent before activation, existing-building surveys

Requirements change. Always confirm the current version with your local fire marshal.

Common ERRCS Requirements Across Texas

Even with local differences, most Texas jurisdictions share the same foundation from IFC Section 510 and NFPA standards:

  • Signal strength and audio quality. A minimum signal of about -95 dBm and a DAQ of 3.0 are common benchmarks.
  • Critical areas. Fire command centers, fire pump rooms, stairwells, exit passageways and elevator lobbies get extra attention during testing.
  • Backup power. Battery backup to keep the system running during a power outage.
  • Listed equipment. FCC-certified, UL 2524-listed amplifiers.
  • Radio licensee consent. Under FCC rule 47 CFR 90.219, boosters on public safety frequencies need the consent of the radio system licensee and must be registered with the FCC.
  • Testing. Acceptance testing before occupancy and annual inspections after.

How the ERRCS Process Works in Texas

  1. Confirm the AHJ. Find out which city or county fire marshal covers your address and request their current ERRCS requirements.
  2. Run an RF grid test. Test once the building envelope is complete to see whether coverage already passes. Learn more about RF grid testing.
  3. Design and permit. If the building fails, design the system to local rules and submit plans, including any PE seal or registration your city requires.
  4. Coordinate with the radio system owner. Get the frequencies and licensee consent for your jurisdiction’s public safety radio network.
  5. Install and test. Install the system, then complete acceptance testing witnessed by the fire department before the Certificate of Occupancy.
  6. Stay compliant. Schedule annual testing and keep records on site. See our ERRCS testing services.

Avoid Delays on Your Texas Project

  • Test early. Waiting until the end of construction leaves little time to design, permit and install if your building fails.
  • Read the local rules. Houston’s PE seal and registered inspector, Austin’s GROL and 12-hour battery, and San Antonio’s contractor registration can each add steps.
  • Plan for remodels and lease buildouts. In Houston, these can trigger ERRCS requirements too.
  • Start radio coordination during design. Frequency and licensee approvals can take time.

Frequently Asked Questions

Does Texas have a statewide ERRCS law?
No. Texas cities adopt and amend the International Fire Code locally, and some larger counties adopt a fire code for areas outside city limits. Requirements depend on where your building is located.
Is ERCES the same as ERRCS?
Yes. ERRCS, ERCES, ERCC and two-way radio enhancement system all describe the same type of in-building system that carries first responder radio signals.
Do existing buildings in Texas need an ERRCS?
It depends on the city. Houston applies its rules to remodels and lease buildouts, and San Antonio can require coverage surveys and upgrades in existing buildings.
Who can design and install an ERRCS in Texas?
It varies by city. Houston requires Texas PE-sealed plans and registered inspectors. Austin requires a GROL and in-building training. San Antonio accepts a GROL, NICET, ETA DAS certification or an approved PE, and requires the installer to register with the City.
How often does an ERRCS need to be tested?
Most jurisdictions require acceptance testing before occupancy and annual testing after that, plus testing after changes that could affect coverage.

ERRCS Installation and Testing Across Texas

RFE Communications is headquartered in Irving, TX. We design, install, and test ERRCS across Texas, from DFW to Houston, Austin, and San Antonio. Our FCC GROL and NICET-certified team handles grid testing, design, permitting and fire marshal coordination. Learn more about our Texas services.

Building in Texas?
Get a grid test, design and installation plan that meets your city’s ERRCS requirements.
Request a Quote